Culvert design and consent guide

Prepare a site-specific culvert design statement, hydraulic comparison and drawing schedule for ordinary watercourse consent in England or Wales.

Before you start

Prepare one statement per crossing. Bring the authority’s current application form, survey and drawings, hydrology, hydraulic results and outline method statement. Record file numbers and revisions so each conclusion can be checked. Explain any item outside your agreed scope.

Use the statement as an attachment to the authority’s form. Submit drawings and model files separately. This writer records your engineering assessment and flags gaps. The applicant and appointed professionals retain responsibility for design and submission.

In Scotland check SEPA water authorisations; in Northern Ireland check DfI Rivers Schedule 6 consent.

The draft is saved in this browser as you type.

Site and consent route

Locate the crossing on the statutory map and the internal drainage district map. In England the relevant body for an ordinary watercourse is normally the IDB inside its district or the LLFA elsewhere. A council may act under a delegation. For this consent check, “IDB watercourse” means an ordinary watercourse inside an IDB district. Selecting either answer sets the other. Confirm maintenance responsibility separately with the board. Record who confirmed the route.

Need and alternatives

Explain why this crossing is needed here. Map the open channel, a clear-span crossing, use of an existing crossing and any shorter alignment. Compare effects on water levels, habitats, access and maintenance. For an extension or replacement, describe the condition and capacity of the retained length.

Survey and proposed design

Supply a location plan and scaled existing and proposed layouts. Plot sections upstream, at the structure and downstream, looking downstream. Show the channel long section on one datum through both ends of the crossing. Mark the survey extent, nearby controls and the lowest escape route for floodwater.

Hydrology and hydraulic assessment

Agree the design events, design life and acceptable impact with the authority. Identify whether flow is controlled by the inlet or by the barrel and downstream level. In flat or pumped catchments, a managed ditch level, pump controls or a tide can govern headwater. A full-bore pipe calculation alone cannot establish upstream flood levels.

What makes a hydraulic comparison checkable?

Give the flow in m³/s, the downstream level and datum, and identify the cross section or model node at which headwater is reported. State which control governs and how the inlet shape, barrel losses and outlet level were represented. Show where water leaves the channel if capacity is exceeded and whether risk moves to a neighbour.

For example, if existing and proposed headwater at the same node are 8.42 and 8.47 m on the same datum, the change is +0.05 m. Explain what that means against the surveyed bank, access and property levels. The illustration sets no acceptable rise.

Environment, construction and maintenance

Check low-flow passage as well as flood conveyance. Explain how bed material and bank habitat will continue through the crossing, whether the outlet may perch and what happens during construction. Justify any screen against blockage and public safety risks. Identify who can safely inspect and clear the asset after a flood.

Scenario results

Enter comparable existing and proposed results at the same location, for the same event, boundary assumptions and datum. Add a row for each comparison. A positive difference means the proposed water level is higher. The stated change is simple subtraction, in metres. It does not determine culvert capacity or consent acceptability.

Evidence schedule

List the location plan, general arrangement, cross sections, long section, calculations, construction method and maintenance plan as applicable. Record what accompanies this revision.

Review and print

National guidance and method references

  1. Land Drainage Act 1991, section 23 (as amended)

    Statutory starting point for erecting a culvert or altering one in a way likely to affect ordinary watercourse flow. Confirm the application route for temporary works too.

  2. Environment Agency. Owning a watercourse (England)

    Identify the relevant risk management authority. Record the permit or consent discussion before finalising the design.

  3. Environment Agency. Statutory Main River Map (England)

    Check the designation at the actual crossing. Watercourse size or appearance is an unreliable guide.

  4. Association of Drainage Authorities. Internal Drainage Boards directory

    Find the board, then verify the district boundary, local byelaws and access requirements with it.

  5. Natural Resources Wales. Main rivers

    Check designation in Wales. Main river works follow the relevant NRW permitting route.

  6. Natural Resources Wales. Apply for land drainage consent

    NRW handles ordinary watercourse consents within Welsh internal drainage districts. Elsewhere on ordinary watercourses check with the LLFA.

  7. Benn, J., Kitchen, A., Kirby, A., Fosbeary, C., Faulkner, D., Latham, D. and Hemsworth, M. (2019). Culvert, screen and outfall manual. CIRIA C786. ISBN 9780860178910.

    UK whole-life technical reference covering design, operation and ownership. Supersedes C689 and the earlier Environment Agency trash and security screen guide.

  8. Environment Agency. Flood estimation guidelines

    Document the source, choice and checks on design flows, including uncertainty.

  9. Environment Agency. Using modelling for flood risk assessments

    Technical context for model extent, boundary conditions, baseline comparison and sensitivity. Agree a proportionate scope with the consenting body.

  10. Environment Agency. Flood risk assessments: climate change allowances (England)

    Record the purpose, catchment, allowance, epoch and lifetime. Use the guidance applicable to the project and jurisdiction.

  11. FHWA (2012). Hydraulic Design of Highway Culverts, third edition, HDS 5, FHWA-HIF-12-026

    Technical source for inlet and outlet control analysis. Check coefficients, shape, units and applicability when citing it. UK consenting criteria come from the relevant authority.

  12. Environment Agency. Blockage management guide, project SC110005 (completed 2019)

    Assess the source of debris, how likely it is to lodge, consequences and options for intervention. Evidence the blockage scenario selected for the site.

  13. SEPA. Engineering in the Water Environment: River Crossings, WAT-SG-25

    Technical reference for crossing options, bed continuity and fish passage. Scottish permitting rules have a separate territorial scope.